Chemical-Free Oil Removal: How CDFU Makes Dissolved Air Do the Demulsifying
Most oily wastewater treatment starts with a dosing skid. Coagulant, then flocculant, then a pH adjustment, then a polymer to hold the floc together. Each chemical solves a separation problem and creates a sludge problem, and the sludge is where the cost hides: dewatering, trucking, incineration, and the liability that follows the ash.
CDFU was designed to skip that sequence. Its demulsification mechanism is physical, and the only consumable is electricity.
Three technologies in one shell
SINOKLE builds the unit around cyclonic dissolved air flotation rather than around chemistry, and the architecture follows from that choice.
The unit integrates centrifugal separation, dissolved air flotation and ultrafine bubble generation. That is not a marketing list; each element does a specific job that the other two cannot.
Centrifugal separation handles the heavy fraction quickly, throwing dense solids outward so they never reach the flotation zone. Dissolved air flotation provides the lifting mechanism for everything lighter than water. Ultrafine bubble generation is the enabling step, because the bubble size determines what can be attached and lifted at all.
Bubbles at 5-30 μm, and why the size matters
Through a special structural design the unit produces ultrafine bubbles with diameters between 5 and 30 μm. At that scale the bubbles are uniformly dispersed, highly adsorptive, and slow-rising — which is exactly what is needed to intercept droplets that are themselves only a few microns across.
A conventional induced-gas system produces millimetre bubbles. Those rise fast, create surface turbulence and carry only the large droplets they happen to hit. The fine emulsion passes straight through and out with the effluent, which is why so many plants report good removal on free oil and poor removal on everything that matters.
Two zones, two jobs
Oily wastewater is mixed with DAF water that releases a large number of ultrafine bubbles through a release device. The mixture enters the swirl separation zone tangentially, where strong centrifugal force separates heavy suspended solids first. It then enters the flotation separation zone, where dispersed oil, emulsified oil and suspended solids are attached by ultrafine bubbles, demulsified and aggregated under swirl action, then rise and are discharged as a concentrated froth.
Order matters here. If flotation came first, the heavy solids would load the bubble field and steal attachment sites from the oil. Taking them out tangentially first leaves the bubble population for the oil, which is the harder target.
Performance, stated without adjectives
- Single-stage oil removal efficiency above 90%.
- Suspended solids removal above 85%.
- Effluent oil content stably controlled below 5 mg/L.
- Retention time of 1-5 minutes, which is 3 to 8 times the efficiency of conventional flotation processes.
- No chemical dosing anywhere in the line.
The retention time figure is the one that changes project economics. A conventional flotation cell needs 20 to 30 minutes of residence to do less work; this unit needs a few minutes, so the steel, the building and the pump energy all shrink together.
What happens to the oil
Because no coagulant is added, the oily sludge that would normally be generated is fundamentally eliminated. What comes off the unit is a concentrated waste oil with re-refining value rather than a chemically contaminated sludge with disposal cost. The environmental benefit and the economic benefit are the same benefit, seen from two sides.
The unit also runs fully enclosed and pressurised, so odour cannot escape. That detail matters more than it sounds: an open flotation cell in a refinery or a municipal plant is an odour source, and odour complaints are what turn a technical success into a political problem.
A refinery in Xinjiang, as an example
At a black water treatment project at an oil refinery in Xinjiang, the process chosen was a coalescing pressure oil remover followed by CDFU cyclonic dissolved air flotation. Demulsification and oil removal were achieved entirely by physical means: no chemical dosing, no sludge generation, no secondary pollution, and the recovered oil goes back for re-refining. The economics of that project rest on the third point as much as on the first two.
A note on where CDFU does not fit
Physical separation has boundaries, and pretending otherwise is how a good technology acquires a bad reputation. Very high free oil arriving as a thick layer is better skimmed before it reaches the unit, otherwise the froth handling becomes the bottleneck. Water with heavy scale-forming chemistry needs the release device protected, because a blocked nozzle stops bubble generation and the unit turns into an expensive settling tank. Neither condition rules out CDFU; both change what goes in front of it.
Where the footprint argument wins
CDFU is skid-mounted with a footprint about a third of conventional equipment. Onshore that is a saving. Offshore it is the difference between a viable project and a rejected one, because platform deck area is the scarcest input in the design. The modular structure simplifies installation and shortens construction, and the control system, built on IoT and AI functions, supports remote monitoring and unattended operation.
Physical separation has been dismissed for years as less effective than chemistry. On emulsified oil the opposite is now true: the chemistry removes water and creates sludge, while the bubble does the work and returns the oil.