Home News Knowledges First Start-Up of a Demineralised Water Station: RO and Mixed-Bed Sequence

First Start-Up of a Demineralised Water Station: RO and Mixed-Bed Sequence

2026-11-24 4 readings

A demineralised water station that feeds a process unit is not a set of independent skids. Multi-media filtration, cartridge filtration, reverse osmosis and mixed-bed polishing are commissioned in one fixed sequence, and skipping an early step shows up much later as fouled membranes or off-spec product water. The cost of rushing — energising the high-pressure pump too early, closing the concentrate valve before the line is flushed — is measured in membrane elements, not in hours.

Pre-Start: Chemicals, Machines, Readiness

Three groups of checks come before anything is switched on. Chemicals first: prepare flocculant, scale inhibitor and ammonia solutions to their required concentrations in advance, and confirm every water tank has reached its specified level, because a station that starts with empty tanks will be restarted within the hour.

Machines next. Verify metering pump accuracy, confirm centrifugal pumps, Roots blowers and all static equipment valves open and close freely, check lubricant levels on every rotating machine, and bar the rotating machines over by hand to prove nothing is jammed and the shaft turns freely.

Readiness last, and this is where most first runs lose time:

  • MCC cabinet closed and energised, all local control cabinets energised;
  • all instruments initially calibrated, accurate and in service;
  • chemical dosing units charged with prepared solution;
  • raw water supply available for service;
  • all water tanks inspected and available, with outlet valves open;
  • inlet valves on the intermediate water pump, demineralised water pump and backwash pump open.

From Raw Water to Cartridge Outlet

Set every control cabinet selector to manual. Open the multi-media filter inlet valve and upper drain, start the raw water pump, and when water appears at the upper drain open the vent valve and close the upper drain. The filter must run full of water — a partly filled bed channels and passes solids straight through. When water shows at the vent, open the lower drain and sample the forward-flush water: turbidity must be below 1 NTU before the outlet valve is opened and the lower drain closed. That number is not a formality, it is the acceptance test for the whole filtration stage.

With outlet water on specification, open the cartridge filter inlet and discharge valves and throttle the discharge so cartridge inlet pressure stays below 0.2 MPa. Do not move on until cartridge effluent is acceptable; anything that passes here reaches the membranes, and membrane fouling is not reversible by adjustment.

The RO First Run: Order Matters More Than Settings

Open the permeate discharge and concentrate discharge valves, then the RO feed valve and feed control valve. After water appears at the concentrate discharge, flush for 3–5 minutes and close the concentrate discharge valve. Close the feed valve, set the feed control valve to half open and set the concentrate control valve.

Now start the high-pressure pump. This is the single most damaging step to get wrong: starting the pump with feed and concentrate discharge valves open can cause irreversible damage to the membrane elements, which is why the interlock is built around a closed feed valve and a half-open feed control valve.

Open the RO feed valve and adjust the concentrate control valve until feed pressure reaches 1.4 MPa. Run for 10 minutes, record feed and permeate conductivity, and calculate both figures rather than judging by eye. Recovery is permeate flow divided by permeate flow plus concentrate flow, expressed as a percentage; salt rejection is one minus permeate salt concentration divided by feed salt concentration. Because conductivity meters report conductivity only, feed and permeate conductivity stand in for the salt concentrations. Salt rejection above 98% means the RO unit is running normally.

Polishing, pH and Deaeration

Open the intermediate tank outlet and start the intermediate low-pressure pump to supply the methanol wash column, desulphurisation and isobaric recovery sections. For the mixed bed, open inlet and vent valves with all other valves confirmed closed, start the intermediate water pump, close the vent when water appears and open the lower drain. When mixed-bed effluent conductivity falls below 0.2 µS/cm, open the outlet and close the discharge.

Trim the ammonia metering pump so that demineralised water pH sits at 8.5–9.2, which is what shift conversion and ammonia synthesis require. Then start the demineralised water low-pressure pump on the standard centrifugal procedure and supply the shift conversion water heater. Open the deaerator inlet, steam inlet and discharge valves for thermal deaeration; when water temperature reaches 104 °C, close the discharge valve and open the outlet. Finally start the medium-pressure and high-pressure pumps to feed the methanol soft water heater, the ammonia synthesis waste heat boiler, the gasifier jacket, the waste heat boiler and the power plant.

Five Decisions That Decide the First Run

Rinse before you pressurise. The multi-media forward flush must reach below 1 NTU and the RO concentrate line must be flushed for 3–5 minutes before that valve is closed; skipping either pushes debris and air into the membranes. Protect the high-pressure pump interlock and never defeat it for convenience. Verify performance numerically: record conductivities at 10 minutes and calculate recovery and rejection instead of trusting a clear-looking permeate. Control pH at the polishing stage, where mixed-bed conductivity below 0.2 µS/cm proves resin performance and ammonia dosing sets 8.5–9.2 for downstream users. Deaerate at temperature, because thermal deaeration is complete only at 104 °C.

None of these steps is difficult. What separates a clean commissioning from a difficult one is doing them in the order written, with the acceptance criteria recorded as numbers at each stage.